118043/FUL/25 decided approve with conditions Last updated 15/02/2026, 12:01

Development of infrastructure for a 400kV grid connection bay, including busbars, conductors, disconnectors, circuit breakers, transformers, surge arrestors, a relay room, earthing systems, cabling, and other equipment to connect a Battery Energy Storage System to the National Grid.

Full Application

Isherwood Road, Carrington, Manchester, M31 4BH

M31 4BH

Full Proposal

Development of power related infrastructure to deliver a 400kV grid connection bay, comprising busbars, conductors, disconnectors, circuit breakers, instrumental transformers, surge arrestors, a portable relay room, earthing systems, cabling and other associated equipment to complete grid connection between consented Battery Energy Storage System and the National Grid.

Application Timeline

Application Registered
22/12/2025
Application Validated
22/12/2025
Target Decision Date
16/02/2026
Committee Date
N/A
Decision Made
15/02/2026
Decision Issued
15/02/2026

Applicant

Mr Adam Moran