Application to develop a containerised Battery Energy Storage System with battery units, transformer units, inverter cabinets, switchgear buildings, internal access tracks, electrical substation compound, CCTV, emergency/security lighting, perimeter fencing, underground surface water drainage, vehicular parking area, site welfare facilities, underground cable connection, widening of Ashton Road, and other associated infrastructure.

Full Application

Carrington

Full Proposal

Proposed development of a containerised Battery Energy Storage System comprising battery units with transformer units and inverter cabinets, switchgear buildings, internal access tracks, electrical substation compound including transformers, switchgear, and associated equipment, CCTV and emergency / security lighting, perimeter fencing, underground surface water drainage infrastructure, vehicular parking area, site welfare facilities, underground cable connection, widening of Ashton Road and other associated infrastructure.

Application Timeline

Application Registered
11/12/2024
Application Validated
16/12/2024
Target Decision Date
17/03/2025
Committee Date
N/A
Decision Made
15/05/2025
Decision Issued
15/05/2025