115160/FUL/24 decided approve with conditions
Last updated 20/07/2025, 14:55
Application to develop a containerised Battery Energy Storage System with battery units, transformer units, inverter cabinets, switchgear buildings, internal access tracks, electrical substation compound, CCTV, emergency/security lighting, perimeter fencing, underground surface water drainage, vehicular parking area, site welfare facilities, underground cable connection, widening of Ashton Road, and other associated infrastructure.
Full Application
Carrington
Full Proposal
Proposed development of a containerised Battery Energy Storage System comprising battery units with transformer units and inverter cabinets, switchgear buildings, internal access tracks, electrical substation compound including transformers, switchgear, and associated equipment, CCTV and emergency / security lighting, perimeter fencing, underground surface water drainage infrastructure, vehicular parking area, site welfare facilities, underground cable connection, widening of Ashton Road and other associated infrastructure.
Application Timeline
- Application Registered
- 11/12/2024
- Application Validated
- 16/12/2024
- Target Decision Date
- 17/03/2025
- Committee Date
- N/A
- Decision Made
- 15/05/2025
- Decision Issued
- 15/05/2025
Case Officer
Applicant
SSE Daines BESS